Sep 15 2014 | Project Watch

Durg Bypass Road Project



Project Details Work of Construction, Maintenance and Operation of Durg bypass on NH – 6 on
BOT basis in State of Chhattisgarh under NHDP Phase III
Name of Authority National Highways Authority of India
Concessionaire SMS Infrastructure Ltd, Nagpur
Independent Engineer S. N. Bhobe Associates Pvt. Ltd (T: 022-2783 1070)
Total Project Cost Rs 127.94 Crore
Date of Signing of Concession
Agreement
05th November 1997
Date of Commencement 21st April 2011
Date of Completion 730 Days From Appointed Date.
Scheduled Date of Completion 30th September 2013
Current Status (As on 20/05/2014) 87.02 per cent work completed. Completion is targetted by 30th September 2014
Contacts B. N. Singh, General Manager Technical, agra@nhai.org, M: 9012 140 777