Apr 15 2015 | Project Watch

4 Laning of Mulbagal - Andra Pradesh / Karnataka border section

Project Details 4 Laning of Mulbagal - Andra Pradesh / Karnataka border section of NH-4 from Km 216.912 to Km 239.100 in the State of Karnataka to be executed on design, build, finance, operate and transfer (DBFOT / BOT) basis in
BOT (Toll) mode under NHDP Phase III
Name of Authority National Highways Authority of India
Concessionaire JSR Mulbagal Tollways Pvt Ltd
Independent Engineer Artefact Projects Ltd
Project Cost Rs. 154.01 Crore
Concession Agreement Signing Date 2nd May 2012
Date of Commencement 22nd May 2013
Concession Period 29 years (Including Construction Period of 365 days)
Length Of Project Stretch 22.188 KM
Scheduled Date of Completion 21st May 2014 (365th day)
Revised Date of Completion 31st April 2015
Current Status 96 per cent work is completed
Contacts Surendra Kumar, Project Director, NHAI, Bangalore,
T: 080-28394403, 28394383, M: 9901976111, nhaibangalore@gmail.com,