May 1 2015 | Project Watch

Four laning of Ranchi - Rargaon - Jamshedpur section

Project Details Four laning of Ranchi - Rargaon - Jamshedpur section from km 114.000 to km 277.500 of NH-33 in the State of Jharkhand on design, build, finance, operate and transfer (DBFOT) annuity basis under NHDP phase-III project.
Name of Authority National Highways Authority of India
Concessionaire Ranchi Expressways Ltd
Independent Engineer Aarvee Associates Architects Engineers & Consultants Pvt. Ltd.
Project Cost Rs. 1479 Crore
Concession Agreement Signing Date 20th April 2011
Date of Commencement 4th December 2012
Concession Period 12.5 years (Including 2.5 years Construction Period)
Scheduled Date of Completion 4th June 2015
Current Status 17 per cent work is completed
Contacts Manoj Kumar Pandey, Project Director, NHAI, Ranchi-834002, (Jharkhand),
T: 0651-2245293, M: 9431711197, 9431376682, nhairanchi@gmail.com