May 15 2015 | Project Watch

Four laning of Solapur-Maharashtra/Karnataka section

Project Details Four laning of Solapur-Maharashtra/Karnataka border section of NH-9 from km 249.000 to km 348.800 (Design length 100.060 km) in the state of Maharashtra on design, build, finance, operate and transfer(DBFOT) basis under NHDP phase-III. under NHDP phase-III.
Name of Authority National Highways Authority of India
Concessionaire Coastal & Srei
Independent Engineer Artefact Project Ltd
Project Cost Rs. 923.04 Crore
Concession Agreement Signing Date 29th February 2012
Date of Commencement 3rd June 2014
Concession Period 25 years (Including 30 months Construction Period)
Scheduled Date of Completion 28th November 2016
Current Status 10 per cent work is completed
Contacts B. B. Ikhe, Project Director, NHAI, Solapur - 413 003, (Jharkhand), T: 0217-2303379, M: 8805011173, solapur@nhai.org