Jun 15 2015 | Project Watch

Two laning of Motihari - Raxaul Section

Project Details Two laning of Motihari - Raxaul Section of NH-28A from Km 0.600 to Km 62.064 and link road from Km 62.064 to ICP Raxaul in the State of Bihar under NHDP-III on design, build, finance, operate, and transfer (DBFOT) toll basis.
Name of Authority National Highways Authority of India
Concessionaire Tantia Raxaul Tollway Pvt Ltd
Independent Engineer Frischmann Prabhu India Pvt Ltd
Project Cost Rs. 429 Crore
Concession Agreement Signing Date 15th April 2011
Date of Commencement 10th October 2011
Concession Period 20 years (Including 910 days of construction period)
Scheduled Date of Completion 8th April 2014
Revised Date of Completion 31st March 2016
Current Status 39.02 per cent work is completed
Contacts Shamim Ahmad, Project Director, NHAI, Muzaffarpur, Bihar 842001. T:
0621-29012447, M: 9430685103, piumuzaffarpur@nhai.org, muz@nhai.org