Sep 1 2015 | Project Watch

Four Laning of Gwalior-Shivpuri Section


Project Details



Four Laning of Gwalior-Shivpuri Section of NH-3 from Km 15.600 of NH-75 (End of Gwalior bypass) to Km 236.00 of NH-3 in the State of MadhyaPradesh on BOT (Toll) on DBFOT basis pattern under NHDP phase - IV.



Name of Authority


National Highways Authority of India


Concessionaire


Essel Gwalior-Shivpuri Toll Roads Pvt Ltd


Independent Engineer


CDM Smith India Pvt Ltd


Project Cost


Rs.1055 Crore


Concession Agreement Signing Date


9th January 2012


Date of Commencement


16th May 2013


Concession Period


29 years


Construction Period


910 days from Appointed date


Scheduled Date of Completion


11th November 2015


Current Status


65-70 per cent work is completed


Contacts


Anil Kumar Jain, Project Director, Shivpuri-473551, Madhya Pradesh.