Sep 1 2015 | Focus

Clean Energy

50 000 MW Hydroelectric Initiative (DPR Prepared)


S. No


Scheme

State

I. C. (MW) Asper PFR

I. C. (MW) Asper DPR

Agency

Remarks

1.
Bajoli Holi

Himachal Pradesh 180.00 180.00
GMR Energy
Ltd.


Under Construction

2. Chhatru Himachal Pradesh

108.00 108.00
DSCL Ltd.

DPR concurred by CEA

3. Luhri Himachal Pradesh

465.00 776.00
SJVNL

DPR prepared. Returned for resubmission.

4. Tidong-I Himachal Pradesh 60.00 100.00
Nuziveedu
seeds

Under construction
5. Kawar J&K 320.00 520.00
NHPC

DPR prepared, under examination CEA

6.
Kiru J&K 430.00 660.00
NHPC

DPR prepared, under examination CEA

7. Ratle J&K 560.00 690.00
NHPC

Under Construction

8. Ujh J&K 280.00 212.00
CWC

DPR prapared

9. Badrinath
(Alaknanda)
Uttarakhand 140.00 300.00
GMR Energy
Ltd.
DPR concurred for 300 MW by CEA 08.08.2008.
Accorded by MOEF.
10. Bhaironghati Uttarakhand 65.00 381.00
UJVNL

DPR prepared for 381 MW. Returned for resubmission.

11. Bogudiyar -
Sirkari Bhyal
Uttarakhand 170.00 146.00 GVK-L&T
(Goriganga Hydro Power
Ltd.)
DPR prepared. Returned for resubmission.
12. Devsari Uttarakhand 300.00 252.00
SJVNL

DPR Concurred by CEA on 07.08.2012.


13.

Gangotri Uttarakhand 55.00

UJVNL

DPR prepared. Included in Bhaironghati HEP.

14.
Harsil Uttarakhand 210.00

UJVNL

DPR prepared. Included in Bhaironghati HEP.

15. Jelam Tamak Uttarakhand 60.00 108.00
THDC

DPR submitted in Dec.,2012 and under
examination in CEA.
16. Rupsiabagar Uttarakhand 260.00 261.00
NTPC

DPR concurred for 261 MW by CEA

17. Uttarakhand Uttarakhand 310.00 171.00
NTPC

Under Construction

18. Nand Prayag
Langashu
Uttarakhand 141.00 100.00
UJVNL

DPR for 100 MW submitted in March.

19. Naitwar-Mori Uttarakhand 33.00 56.00
SJVNL

DPR approved for 60 MW by State Govt.

20. Gundia Karanataka 300.00
200.00


KPCL
DPR prepared for 400 MW. Concurred by CEA for 200
MW on 25.08.2008.
21. Attunli Ar.Pradesh 500.00 680.00 Jindal Power
ltd.

DPR under exmination in CEA

22. Demwe Ar.Pradesh 3000.00 2890.00 Athena
Demwe
Projects Ltd.
Demwe lower (1750 MW) DPR prepared & Concurred.DPR of Demwe upper (1140 MW) returned to project
authorities.
23. Etalin Ar.Pradesh 4000.00 3097.00 Jindal Steel &
Power

DPR Concurred by CEA on 12.7.2013.

24.
Hirong Ar.Pradesh 500.00 500.00 Jaiprakash
Power Ltd.

DPR Concurred by CEA on 10.4.2013.

25. Hutong Ar.Pradesh 3000.00 1200.00
Mountain Falls
Ltd.

DPR of Hutong-II (1200 MW) Returned in May’12
Hutong-I (588 MW) abandoned. Issue of Storage Vs
RoR to be shorted out.
26. Kalai Ar.Pradesh 2600.00
2650.00 Mountain Falls
Ltd. / Reliance
Power Ltd.

DPR of Kalai-I (1450 MW) returned for resubmission
and DPR Of Kalai-II concurred by CEA on 27.3.15.

27. Naying Ar.Pradesh 1000.00 1000.00 D.S.
Construction
Ltd.
DPR Concurred by CEA on 31.07.2013.
28.

Tato-II

Ar.Pradesh 700.00 700.00
Reliance
Power Ltd

DPR Concurred by CEA on 22.05.2012.
SI. Scheme State
I. c. (MW) As per PFR

I. C. (MW) Asper DPR
I. C. (MW) Asper DPR

Remarks

29. Badao Ar.Pradesh 120.00 60.00 Coastal
Projects Pvt.
Ltd.
DPR earlier prepared by NEEPCO, Project has
allotted to Coastal Projects Pvt, Ltd, DPR to be
prepared again.
30.
Dibbin Ar.Pradesh 100.00 120.00 KSK Electricity
Financing India
Ltd.
DPR Concurred by CEA for 120 MW on 04.12 2009.
31. Phanchung Ar.Pradesh 60.00
56.00

India bulls
Real Estate
Ltd.
DPR submitted to State Govt.
32. Pakke Bung-I Ar.Pradesh 110.00 40.00
EDCL

DPR submitted to State Govt.
33. Simang Ar.Pradesh 90.00 133.00
Adishankar
Power Pvt. Ltd.

DPR submitted to State Govt. The project is being developed in two stages of Simang-I (67 MW] and Simang-II (66 MW)
34. Talong Londa Ar.Pradesh 300.00 225.00 GMR Energy
Ltd.

DPR Concurred by CEA on 30.04.2013.

35. Tarangwarang Ar.Pradesh

30.00

36.00 India bulls
Real Estate
Ltd.

DPR submitted to State Govt.
36. Dikhu Nagaland 140.00 186.00 Manu Energy
Pvt. Ltd.

DPR Concurred by CEA on 11.02.2014.

37.
Mawhu Meghalaya 120.00 90.00
NEEPCO


DPR prepared for 90 MW
38. Dikchu Sikkim 105.00 96.00 Sneha kinetic
Projects.Ltd

Under construction

39. Panan Sikkim 200.00 300.00 Himigiri Hydro
Pvt. Ltd.

Under construction

40. Rongnichu Sikkim
195.00

96.00 Madya Bharat
Power Co. Ltd.
Under construction, As per PFR the project isindentified as Rogni Storage of 195 MW.


Total

21317.00 19376.00