Dec 1 2015 | Project Watch

Four Laning of Pathankot - Amritsar Section

Project Details

Design,engineering, finance, construction, operation and

maintenance of Pathankot to Amritsar section of NH-15 from Km. 6.082 to Km.

108.502in the state of Punjab under NHDP phase III on design, build,

finance, operate and transfer DBFOT basis.

Name of Authority National Highways Authority of India
Concessionaire IRB Toll Road Pvt Ltd
Independent Engineer ICT Pvt Ltd
Project Cost Rs. 705 Crore
Concession Agreement Signing Date 16th November 2009
Date of Commencement 31st December 2010
Concession Period 20years
Construction
Period
910days from appointed date 27th June 2013, Requested for EOT upto oct
2014
Date of Completion 27thFebruary 2015
RevisedCompletion Period February2016
Current
Status
The project is about to complete in February 2016
Contacts BS Chouhan, Manager Technical, 135, Guru Amar Dass Nagar,
Jalandhar-144008, Punjab. T: 0181-2603627,M: 9814402236,
8872011719, nhaijal181@yahoo.in,
(Co.,NK Jain, Project
Director)