Jan 1 2016 | Project Watch

6-laning of Barwa Adda – Panagarh section

Project Details

6-laning of Barwa Adda – Panagarh section of NH-2 from Km.398.240 to Km.521.120 including Panagarh Bypass in the states of Jharkhand & West Bengal under NHDP Phase-V on BOT (Toll) on DBFOT pattern

Name of Authority National Highways Authority of India
Concessionaire Barwa Adda Expressway Pvt Ltd
Independent Engineer SA Infrastructure Consultants Pvt Ltd
Project Cost Rs.1665 Crore
Concession Agreement Signing Date 8th May 2013
Date of Commencement 1st April 2014
Concession Period 20Years (Including 910 days of construction period)
Date of Completion 26th September 2016
Current Status 35Per Cent work is completed
Contacts

A.Handique, Project Director, PIU-Durgapur,

NHAI Complex, Sector - 2(A), Bidhannagar.

Durgapur-713212, West Bengal. T: 0343-2535766,

2534815, dur@nhai.org, nhaipiudgp@yahoo.com