Feb 15 2016 | India Opportunities

Tunnel Work For Chennai Metro

The tunnelling work for the Chennai metro was abandoned by the Russian company Mosmetrostroy demanding more money. The tunnel boring machines and other equipment left behind by the previous contractor also got damaged during December floods. Chennai Metro Rail Ltd (CMRL) has invited fresh bids to complete the tunnel work. CMRL wants the work to be completed in nine months whereas according to the contractors around 30 months are needed to complete the remaining work.