Feb 15 2016 | Project Watch

4 Laning of Chappra - Hajipur Section

Project Details

Four-laning of Chhapra- Hazipur section of NH-19 from km 143.200 to km 207.200 in the state of Bihar under NHDP III on Design, Build, Finance, Operate and Transfer (DBFOT) Annuity basis.

Name of Authority National Highways Authority of India
Concessionaire Chhapra Hajipur Expressway Ltd
Independent Engineer Stanley Consultant Inc.
Project Cost Rs. 812.5 Crore
Concession Agreement Signing Date 28th July 2010
Date of Commencement 27th January 2011
Concession Period 15 Years (Including 910 days of construction period)
Date of Completion 27th July 2013
Revised Date of Completion 31st March 2016
Current Status 52.7 Per Cent work is completed
Contacts Col. Pranay,Kumar, Project Director, 2nd Floor, Sharma House, Ramashish Chowk, Hajipur (Vaishali)-844101, Bihar. T: 06224-274255, nhaihajipur@gmail.com

Advertise Here [728 W x 90 H pixels]