Mar 1 2016 | Road Sector

6 Laning Of Krishnagiri - Walajahpet Section

Project Details

Six laning of Krishnagiri-Walajapet section of NH -46 from

Km: 0.000 to Km: 148.300 in the state of Tamil Nadu under

NHDP Phase - V to be executed as BOT (Toll) project on

DBFO pattern.

Name of Authority National Highways Authority of India
Concessionaire L&T Krishnagiri-Walajapet Toll way Pvt Ltd
Independent Engineer Roughton International Ltd in JV with
Theme Engineering services (P) Ltd
Project Cost Rs. 1250 Crore
Concession Agreement Signing Date 13th May 2010
Date of Commencement 7th June 2011
Concession Period 30 Years (Including 912 days of construction period)
Date of Completion Dec 2013
Revised Date of Completion Dec 2016
Current Status 96 Per Cent work is completed
Contacts T.Parvateesam, Project Director, 259/1, Salem Main Road,
Near KAKC Petrol Bunk, Krishnagiri-635001 Tamil Nadu. T:
04343-234250, M: 9442275834, kri@nhai.org,
nhaikrishnagiri@gmail.com