Four laning of Hisar to Dabwali section (Package -I)

Project Details

Four laning of Hisar to Dabwali section of NH-10 from Km.170.00 to Km.315.550 under NHDP Phase-IVB (Package -I) in the State of Haryana.

Name of Authority National Highways Authority of India
Contractor GR Infra Projects Ltd
Authority Engineer CEMOSA
Project Cost Rs.549 Crore
Concession Agreement Signing Date 23rd March 2015
Date of Commencement 9th August 2015
Construction Period 913 days
Date of Completion April 2018 8-2-2018
Current Status 44 Per Cent work is completed