Jul 15 2016 | Project Watch

4 laning of Obedullaganj to Betul section

Project Details

Four laning of Obedullaganj to Betul section of NH-69 from km 2.800 to 8.300 and from km 20.700 to km 137.000 (Approx. length 121.36 km) (Excluding wild life sanctuary from km 8.300 to km 20.700) (Except bypass from km 28.000 to km 61.500 as Two Lane with paved shoulder) in the state of MP to be executed as BOT (Toll) project on DBFOT pattern under NHDP phase III.

Name of Authority National Highways Authority of India
Concessionaire Transstroy Obedullaganj-Betul Tollways Pvt Ltd
Independent Engineer Consulting Engineering Group Ltd, Jaipur
Project Cost Rs. 912 Crore
Concession Agreement Signing Date 30th April 2012
Date of Commencement 7th February 2014
Concession Period 30 Years (Including 910 days of construction period)
Date of Completion 6th August 2016
Current Status 1.5 Per Cent work is completed
Contacts M.L.Purbia, Project Director, Plot No. A#43, Sakshi bunglow, Trilanga Shahpura, Bhopal-462039. Madhya Pradesh. T: 0755-4253086, bhopal@nhai.org