Aug 1 2016 | Project Watch

4 laning of Ranchi-Rargaon-Jamshedpur section

Project Details

Four laning of Ranchi-Rargaon-Jamshedpur

section from km. 114.000 to km.277.500 of NH-33 in the state of Jharkhand on design, build, finance,

operate and transfer (DBFOT) annuity basis under NHDP Phase-III project.

Name of Authority National Highways Authority of India
Concessionaire Ranchi Expressways Ltd
Independent Engineer Aarvee Associates Architects Engineers & Consultants Pvt Ltd
Project Cost Rs.1479 Crore
Concession
Agreement Signing Date
20th April 2011
Date of Commencement 4th December 2012
Concession Period 15Years (Including 910 days
of construction period)
Date of Completion 4th June 2015
Revised Date of Completion December 2017
Current Status 26.4Per Cent work is completed
Contacts DK Gupta, Project Director, B-402, Road No. 4C, Ashok Nagar,Ranchi-834002, Jharkhand.p T:
0651-2245293, ranchi@nhai.org