Feb 1 2017 | India Opportunities

Four laning of Solapur-Maharashtra/Karnataka border section

Project Details

Four laning of Solapur-Maharashtra/Karnataka border section of NH-9 from km 249.000 to km 348.800 (Design length 100.060 km) in the state of Maharashtra on design, build, finance, operate and transfer (DBFOT) basis under NHDP phase-III.


Name of Authority National Highways Authority of India
Concessionaire Coastal & Srei
Independent Engineer Artefact Project Ltd
Project Cost Rs. 923.04 Crore
Concession Agreement Signing Date 29th February 2012
Date of Commencement 3rd June 2014
Concession Period 25years (Including 30 months Construction Period)
Scheduled Date of Completion 28th,November 2016
Revised,Date of Completion 2018
Current Status 39per cent work is completed
Contacts Surendra Kumar, Project Director, NHAI, Solapur- 413003,
Maharashtra. T:0217-2303379, M:9901976111, solapur@nhai.org

Advertise Here [728 W x 90 H pixels]