Jul 7 2017 | India Opportunities

Hindon elevated road project is running in delay mode

Ghaziabad development authority (GDA) is undertaking the construction of the 10.3 km Hindon elevated road at a cost of Rs 1,147.6 crore. The road is likely to connect Raj Nagar Extension to UP Gate (near Delhi-Ghaziabad border). The project is running behind schedule as the approval from the Railways to construct the 75-metre overbridge over the railway section near Vasundhara is pending. The overbridge is likely to connect elevated road from both sides.