Project Details Two laning with Paved Shoulders of Raebareli to Jaunpur section (Km 0.000 to Km 166.400) of NH-231 in the state of Uttar Pradesh under NHDP IV on BOT (Annuity) on DBFOT pattern. Name of Authority National Highways Authority of India Concessionaire PNC Raebareli Highways Pvt Ltd Independent Engineer S A Infrastructure consultants Pvt Ltd Project Cost Rs. 569.36 Crore Concession Agreement Signing Date 9th November 2011 Date of Commencement 4th June 2014 Concession Period 7 years (Including construction period of 2 years) Scheduled Date of Completion January 2016 Current Status 80 per cent work is completed Contacts C. M. Diwedi, Project Director, Raebareli, Uttar Pradesh. T: 0535-2702526, M: 8005044371, pdpiuraebareilly@nhai.org
Project Details
Two laning with Paved Shoulders of Raebareli to Jaunpur section
(Km 0.000 to Km 166.400) of NH-231 in the state of
Uttar Pradesh under NHDP IV on BOT (Annuity) on DBFOT pattern.