Project Details Four Laning of Kiratpur to Ner Chowk Section of NH-21 from Km. 73.200 to Km. 186.500 in the state of Punjab and Himachal Pradesh to be executed as BOT (Toll),on DBFOT pattern under NHDP Phase - IV. Name of Authority National Highways Authority of India Concessionaire Kiratpur Ner Chowk Expressway Ltd Independent Engineer Getinsa Ingenieria S.L.Spain Project Cost Rs. 1818.47 Crore Concession Agreement Signing Date 16th March, 2012 Date of Commencement 14th November, 2013 Concession Period Concession Period Date of Completion November 2016 Revised Date of Completion February 2018 Current Status 68.41 Per Cent work is completed Contacts Lt Col Yogesh Chandra, Project Director, NHAI, PIU-Mandi, Bagla Muhal Chakkar, PO Nagchala, Tehsil Balh,,Distt Mandi-175021, Himachal Pradesh. T: 01905-246483,,M: 9805960483, pd.mandipiu@gmail.com