Project Details Two laning with paved shoulders of Sitarganj-Tanakpur Section of NH-125 from Km 0.000 (Km 254.600 Of NH-74) to Km 52.200 in the state of Uttarakhand under NHDP-IV on EPC Mode. Name of Authority National Highways Authority of India Contractor M/S H.G. Infra Engineer (P) Ltd Authority Engineer SA infrastructure Consultants Pvt. Ltd Project Cost Rs. 243.11 Crore Contract Agreement Signing Date 2015 Date of Commencement 2nd September 2015 Contract Period /Defects Liability Period (DLP) 2 Years (Including 4 years DLP) Scheduled Date of Completion 31st March 2018 Date of Completion 2020 Current Status 82.14 per cent work is completed Contacts Col. Sandeep Karki, Project Director, Nirmanjali 23, Friends Enclave, Near Railway Mal Godam, Rudrapur- 263153, Uttarakhand. T:05944-240005, pdpiurudrapur@nhai.org, (Nishant Tripathi, Site Engineer, M: 9999392449)
Project Details
Two laning with paved shoulders of Sitarganj-Tanakpur Section of NH-125 from Km 0.000 (Km 254.600 Of NH-74) to Km 52.200 in the state of Uttarakhand under NHDP-IV on EPC Mode.